Sl. No. Name of Work District Estimated cost Status Handed over on
1 Ramanagaram Taluk sub- jail Bangalore Rural 175.80 Ongoing -
2  Bagalkote District Prison Bagalkote 198.00 Ongoing -
3 Bailhongal 4 Qtrs for Taluk Sub jail Staff Belgaum 14.70 Completed  01/04/05
4 Belgaum 48 Qtrs for Central Prison Staff Belgaum 168.00 Proposed -
5 Huvinahadagali 4 Qtrs for Taluk Sub jail Staff Bellary 14.00 Ongoing -
6 Bellary 30 Qtrs for Central Prison Staff Bellary 105.00 Proposed -
7 Bidar 12 Qtrs for District Prison Staff Bidar 49.00 Completed 18/03/05
8 Aurad 4 Qtrs for Taluk Sub Jail Staff Bidar 14.00 Proposed -
9 Bijapur 30 Qtrs for Central Prison Staff Bijapur 105.00 Proposed -
10 Chamaraja nagar new prison Chamaraja nagar 150.00 Ongoing -
11 N R Pura 4 Qtrs for Taluk Sub Jail Staff Chikmagalur 21.40 Completed 17/12/04
12 Chitradurga District Prison Chitradurga 200.00 Ongoing -
13 Mangalore 18 Qtrs for District Prison Staff Dakshina Kannada 63.00 Proposed -
14 Dharwad 48 Qtrs for Borstal School Staff Dharwad 162.30 Completed  31/03/05
15 Dharwad Expansion and Renovation of Existing Jails : Borstal School Dharwad 265.00 Ongoing -
16 Gadag 6 Qtrs for Taluk Sub jail Staff Gadag 21.00 Ongoing -
17 Gulbarga 36 Qtrs for Central Prison Staff Gulbarga 126.00 Ongoing -
18 Sakaleshpura New Prison Hassan 150.00 Proposed -
19 Hassan 12 Qtrs for DHQ Sub jail Staff Hassan 42.00 Proposed -
20 Haveri Constn. of new prison Haveri 132.00 Ongoing -
21 Madikere District Prison Kodagu 254.50 Ongoing -
22 Kolar 4 Qtrs for DHQ Sub Jail Staff Kolar 14.90 Completed  08/10/04
23 KGF 4 Qtrs for Spl Sub Jail Staff Kolar 16.50 Completed 30/3/05
24 Chinthamani Taluk sub- jail Kolar 125.00 Ongoing -
25 Koppal new prison Koppal 200.00 Proposed -
26 Mandya 8 Qtrs for Sub Jail Staff Mandya 31.50 Completed 15/10/04
27 K R Nagar 4 Qtrs for Taluk Sub Jail Staff Mysore 15.80 Completed 19/10/04
28 Mysore 24 Qtrs for Central Prison Staff- Group A Mysore 84.00 Ongoing -
29 Mysore 24 Qtrs for Central Prison Staff- Group B Mysore 84.00 Ongoing -
30 Raichur 18 Qtrs for District Prison Staff Raichur 64.60 Ongoing -
31 Shimoga 12 Qtrs for District Prison Staff Shimoga 41.70 Ongoing -
32 Tumkur Taluk sub- jail Tumkur 200.00 Ongoing -
33 Tiptur 4 Qtrs for Taluk Sub Jail Staff Tumkur 14.00 Proposed -
34 Udupi Constn. of new prison Udupi 186.00 Ongoing -
35 Karwar 18 Qtrs for District Prison Staff Uttara Kannada 62.40 Ongoing -
36 Karwar Expansion and Renovation of Existing Jails : District Prison Uttara Kannada 211.70 Ongoing -

Total (Rs.)

3782.80    